Pre-Use Checks, Inspections And Thorough Examinations: What LOLER Requires
LOLER and HSE’s guidance describe three levels of checking for lifting equipment, and each does a different job. Pre-use checks catch obvious faults before work starts. Inspections, where appropriate, pick up deterioration between examinations. The thorough examination is the systematic statutory assessment by a competent person that ends in a written report. This guide sets out what each involves, who can do it and what records it leaves.
Pre-use checks and inspections are usually done in-house; for the thorough examinations themselves, a list of your lifting equipment and the site address sent to info@gsbinspections.co.uk is enough for us to price the work, and we aim to reply within 48 hours.
The Three Levels Of LOLER Checking At A Glance
HSE’s page on thorough examinations and inspections of lifting equipment sets out the pattern. Users may need to make simple pre-use checks, for example on lifting chains and slings, or daily checks, for example on lift trucks. In some cases inspections and checks are made regularly, often weekly but sometimes monthly or quarterly, such as the checks an operator makes on their crane. On top of both, employers must ensure lifting equipment is thoroughly examined, normally once or twice a year, though sometimes more or less often.
Pre-Use Checks On Lifting Equipment
A pre-use check is a quick look by the person about to use the equipment: is the sling cut or the chain stretched, is the hook latch working, is the MEWP’s tilt alarm sounding, is the SWL marking legible. It needs no paperwork under LOLER, but a site that records pre-use checks can show the faults were being looked for.
A check that finds a fault should take the item out of use until it has been looked at properly. In our judgement, a quarantine bin or tag for doubtful items is the simplest way to make that happen.
LOLER Inspections Between Thorough Examinations
Regulation 9(3)(b) of the Lifting Operations and Lifting Equipment Regulations 1998 requires that lifting equipment exposed to conditions causing deterioration liable to result in dangerous situations is, if appropriate for the purpose, inspected by a competent person at suitable intervals between thorough examinations. The aim is to make sure health and safety conditions are maintained and deterioration is detected and remedied in good time.
Whether an inspection is appropriate, and how often, depends on the equipment and how hard it works. A crane on continuous production duty is a different case from a jib used a few times a month.
Inspection Records And Defects Under LOLER Regulation 10
Under regulation 10(2), a person making an inspection must notify the employer forthwith of any defect that is or could become a danger, and must make a written record of the inspection as soon as practicable. Regulation 11(2)(b) requires that record to be kept available until the next inspection record is made.
The LOLER Thorough Examination
Regulation 9(3)(a) sets the thorough examination intervals for equipment exposed to deterioration: at least every six months for lifting equipment for lifting persons and for lifting accessories, at least every 12 months for other lifting equipment, or in accordance with an examination scheme, plus each time exceptional circumstances liable to jeopardise safety have occurred.
The thorough examination ends in a written report containing the information in Schedule 1, sent to the employer and to any hire or leasing company. A defect presenting an existing or imminent risk of serious personal injury means the enforcing authority is sent a copy as well.
Who Can Carry Out Each Level Of Lifting Equipment Check
Pre-use checks are normally done by the operator or user. Inspections need a competent person, who can be a trained member of your own staff. For the thorough examination, HSE’s guidance quotes the LOLER Approved Code of Practice: the competent person needs the practical and theoretical knowledge and experience to detect defects and assess their importance, and must be sufficiently independent and impartial to make the examination without fear or favour. HSE adds that this should not be the person who carries out routine maintenance, as they would be assessing their own work.
LOLER Pre-Use Check And Inspection Questions
Is a pre-use check a legal requirement under LOLER?
LOLER does not use the term, but HSE’s guidance says users may need to carry out simple pre-use checks, for example on chains and slings, as part of keeping equipment safe.
Does every piece of lifting equipment need inspections between thorough examinations?
Only where appropriate. Regulation 9(3)(b) calls for inspection by a competent person at suitable intervals between thorough examinations if that is appropriate for the purpose.
How long do we keep inspection records?
Until the next inspection record is made, under regulation 11(2)(b).
Can our own staff carry out LOLER inspections?
Yes, if they are competent for the equipment. The thorough examination needs a competent person with sufficient independence and impartiality, who should not be the person doing the routine maintenance.
Independent LOLER Thorough Examinations From GSB
GSB carries out LOLER thorough examinations of cranes, hoists, forklifts, MEWPs and lifting accessories. We do no maintenance and sell no equipment, so the examination stays separate from the servicing and repair work it may lead to.
Tell us what lifting equipment you have and where, at info@gsbinspections.co.uk, and expect a price inside 48 hours in most cases. Not sure whether something needs inspecting between examinations? Ring 01782 855481 and talk it through with one of GSB’s two directors, the owners of the business and both senior engineers. Our examinations follow SAFed’s code of practice for inspection bodies; GSB is an associate member of the federation.