Some lifting equipment is only as safe as the way it has been put in. An overhead crane on its runway, a hoist on a beam or a lift fixed into a building depends on its supports, fixings and alignment, so Regulation 9 of the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER) requires a thorough examination after installation, and again whenever the equipment is assembled at a new site or location, before it is used. This guide sets out when that applies, how it fits with the first-use rules for new equipment, and what happens to the paperwork.

If you have equipment being installed or moved, send the details and the site address to info@gsbinspections.co.uk and we aim to come back with a quote within 48 hours.

What LOLER Regulation 9 Says About Installation And Relocation

Regulation 9(2) applies where the safety of lifting equipment depends on the installation conditions. In that case the employer must make sure it is thoroughly examined:

  • after installation and before it is put into service for the first time; and
  • after assembly and before it is put into service at a new site or in a new location.

The purpose, in the regulation’s words, is to ensure the equipment has been installed correctly and is safe to operate. This sits alongside the periodic examinations under regulation 9(3): at least every six months for accessories and equipment that lifts people, and at least every twelve months for other lifting equipment, unless an examination scheme sets different intervals. The installation report then gives the latest date for the next examination.

Which Lifting Equipment Depends On Its Installation Conditions

LOLER does not list the equipment, so it comes down to whether the way something is fixed, supported or assembled affects whether it is safe. Typical examples include:

  • Overhead travelling cranes and their runways
  • Jib cranes fixed to a wall or a pillar
  • Monorail beams and the hoists that run on them
  • Platform lifts and goods lifts built into a building
  • Equipment assembled on site, such as tower cranes

HSE’s own examples are a platform lift installed in a building and tower cranes. Free-standing equipment that arrives ready to use, such as a forklift truck or a sling, does not usually fall under regulation 9(2), although the first-use rules below still apply.

New Lifting Equipment And The Declaration Of Conformity

Under regulation 9(1), equipment must be thoroughly examined before an employer first puts it into service, unless it has not been used before and, where a declaration of conformity applies, the employer received that declaration no more than 12 months before putting it into service. HSE’s guidance makes clear that this exemption does not cover equipment assembled on site. A brand-new crane delivered with its declaration still needs examining once it has been installed on your runway, because regulation 9(2) applies on top.

Moving Lifting Equipment To A New Site Or Location

The second limb of regulation 9(2) covers equipment that is taken down and put back up. Relocating a jib crane to another bay, moving a hoist and beam to a new production line, or re-erecting a crane at a different factory all mean the equipment is being assembled in a new location, so it needs a thorough examination before it is used there. A valid periodic report from the old position does not cover the new one, because the fixings, supporting structure and alignment are new.

In a factory move or a layout change the focus is usually on getting production running again. Building the examination into the project plan, after installation and before handover, avoids a crane standing idle while the paperwork catches up.

Lifting Equipment Arriving From Another Business

Regulation 9(4) deals with equipment moving between businesses. An employer must not let lifting equipment leave its undertaking, or use equipment obtained from another undertaking, unless it is accompanied by physical evidence that the last thorough examination required under regulation 9 has been carried out. When you take on second-hand or hired equipment, ask for that evidence. Where the equipment also depends on how it is installed at your site, the regulation 9(2) examination is still needed once it is in place.

What The Installation Examination Report Records And How Long To Keep It

The report follows Schedule 1 to LOLER. For the first examination after installation or assembly at a new site or location, it must say that this is such an examination and, if so, that the equipment has been installed correctly and would be safe to operate. It also records any defect that is or could become a danger, the repair needed and by when, and the latest date for the next thorough examination.

Regulation 11 sets how long to keep it: a report on an examination under regulation 9(2) must be kept until the employer stops using the equipment at the place where it was installed or assembled. Periodic reports are kept until the next report is made or for two years, whichever is later.

LOLER Installation Examination Questions

Does a jib crane moved to another bay need examining again?

Yes, if its safety depends on how it is installed. Assembly in a new location means a thorough examination before it is used there.

Does a new crane with a declaration of conformity need an installation examination?

Yes, where its safety depends on installation. The first-use exemption for new equipment does not cover equipment assembled on site.

Who carries out the installation examination?

A competent person who is sufficiently independent and impartial. HSE’s guidance says this should not be the person who carries out routine maintenance of the equipment.

How long must the installation examination report be kept?

Until you stop using the equipment at the place where it was installed or assembled.

Book An Installation Or Relocation Examination With GSB

We carry out LOLER thorough examinations after installation and relocation, as well as on the periodic cycle, for overhead and jib cranes, hoists, runway beams and lifting accessories. We do not install, service or repair lifting equipment, so the examination is kept separate from whoever put the equipment in. With five engineers we can cover single items and multi-site projects.

Email what is being installed or moved, the expected dates and the site address to info@gsbinspections.co.uk, and we aim to send a quote within 48 hours. Questions before you book? Ring 01782 855481 and you will speak to one of the two directors who own GSB, both senior engineers. We are associate members of the Safety Assessment Federation (SAFed).

About Us

We’re independent engineering inspection company covering the whole of the UK, trusted by over 500 businesses to keep their LOLER, PUWER, PSSR and LEV inspections on track.

Inspections are all we do. We don’t repair, service or sell equipment, so you get a straight, impartial report every time.

Our inspections are overseen by directors who are Chartered and Incorporated Engineers, and backed by a team that’s quick to quote, easy to reach and keeps things moving from first enquiry to final report. It’s why our customers rate us five stars on Google.

We’re Here to Help

Get a FREE Engineering Inspection quote now…

SAFed Associate Member badge

Associate Member Of The Safety Assessment Federation (SAFed)

As an associate member of the Safety Assessment Federation (SAFed), GSB Inspections demonstrates our commitment to complying with industry competency standards and the code of practice set by SAFed. This affiliation emphasizes our dedication to maintaining the highest levels of professionalism, ensuring your safety and peace of mind.

Recent Posts

What Our Customers Say

  • My first contact was with Gary and he dealt with my query and questions brilliantly. He explained the process, it was easy to sort and it went smoothly. Expected contact... read more

    Mrs B
    December 8, 2023
  • Excellent service & communications

    Gary Jackson
    October 8, 2023
  • Been using GSB for a year, great service keeping all our plant and machinery in certification

    James Plant
    September 8, 2023
  • Service, communication, support and advice has been excellent, Garry has gone out of his way to support our school with issues arisen from council maintenance, he has gone out of... read more

    Miss H Morrey
    July 13, 2023
  • Well what a great service Gary provides, always does a very thorough job, can't recommend enough, we always Gary really great guy.

    Daz Griffiths
    May 19, 2023
  • Inspected transferable winch units with, greatly appreciated, additional guidance covering separate requirements for accompanying D shackles and inspection schedule. Very diligent service and great value.

    Andrew Piekarczyk
    March 19, 2023
  • Excellent service very competent knowledgeable and professional staff Would highly recommend

    Carl Eades
    January 19, 2023
  • Great service. Would highly recommend and will use again.

    Jade Furey
    November 19, 2022
  • Gary has been doing our certifications for the last few years. Very professional and very reliable. A**

    Rob Scanlan
    September 19, 2022
  • Great bloke, reliable, informative, pleasure to deal with.

    Gary Jackson
    September 19, 2022

Get Your FREE Engineering Inspection Quote

No middle person, direct contact, fast turnaround.

Please complete the form below to submit your enquiry and one of our team will get back to you. 

info@gsbinspections.co.uk

Quick Reply

Have any questions?​

01782 855481

Usual working hours

Mon-Fri, 8am until 4pm